The scale of T5 Grayslake
T5’s Cornerstone campus is planned for up to 1,200 MW of IT capacity — more than four times the next-largest data center development within 50 miles of Grayslake, and more than the next six largest developments in the region combined.
The scale of T5 Grayslake
T5 Chicago IV would be the largest data center within 50 miles of Grayslake — by a wide margin
Stated/reported IT capacity in megawatts (MW) for T5’s proposed Grayslake campus versus the next six largest data center developments within roughly 50 miles, as publicly reported by the operators or trade press. See sources below.
View as a table
| Facility | Location | Distance | Status | Capacity |
|---|---|---|---|---|
| T5 Chicago IV — “Cornerstone” | Grayslake, IL | At the site | Proposed | 1,200 MW |
| Prime Chicago (ORD01) | Elk Grove Village, IL | ~23 mi | Existing / under construction | 270 MW |
| Compass Datacenters | Hoffman Estates, IL | ~20 mi | Existing / under construction | 200 MW |
| Microsoft Azure | Northlake, IL | ~30 mi | Existing / under construction | 158 MW |
| CyrusOne (CHI1–CHI3) | Aurora, IL | ~42 mi | Existing / under construction | 114 MW |
| Edged Chicago campus | Aurora, IL | ~42 mi | Existing / under construction | 96 MW |
| Chirisa Volo Technology Park | Volo, IL | ~7 mi | Existing / under construction | 28 MW |
Distances are approximate straight-line distances from central Grayslake, IL, calculated from published town coordinates. Not shown: Meta’s DeKalb, IL campus (≈47 mi, operational, 2.4 million sq ft per The Real Deal) — Meta has not publicly disclosed its MW capacity, so it isn’t comparable on this chart. Yorkville, IL’s planned “Project Cardinal” campus (≈53 mi, reportedly up to 1,800 MW at full build-out) falls just outside the 50-mile radius and is also excluded. Sources: T5 Data Centers public project materials; Prime Data Centers; Compass Datacenters; CyrusOne; DatacenterDynamics; Baxtel facility tracker; DataCenterMap; Data Center Frontier.
← Back to the home page · Read the full facts
Figures above reflect publicly reported or operator-stated IT capacity for each facility. If any figure here is out of date or wrong, tell us at info@no2hdc.org and we will correct it.